Ahmad Yousefi Hanoomarvar; Maghsoud Amiri; Laya Olfat; Alireza Naser Aadrabadi
Abstract
Purpose: The proposed model is a time-cost-quality trade-off model with three objective functions: minimizing project completion time, minimizing total project cost, and maximizing total quality of activities in a PERT network with multi-mode activities.
Methodology: After presenting the appropriate ...
Read More
Purpose: The proposed model is a time-cost-quality trade-off model with three objective functions: minimizing project completion time, minimizing total project cost, and maximizing total quality of activities in a PERT network with multi-mode activities.
Methodology: After presenting the appropriate mathematical model, based on the design of the experiments, the possible levels of each decision variable were determined. Then, using the simulation process, random values of decision variables and response variables were obtained each time, and by using neural networks, we established a neural network model. To solve this model, two algorithms NSGA-II and MOPSO were used.
Findings: To evaluate the efficiency of the model, the designed model was implemented in the maintenance department of Abtin Ardakan Steel Company. According to the results, it is found that the NSGA-II algorithm has better performance than the MOPSO algorithm.
Originality/Value: In this paper, a model was presented that by eliminating unrealistic assumptions and taking into account the realities of the project is closer to reality than the models presented in this field and has more application in practice.